GS Readiness: End-To-End tests
End-to-end SMOC/Observatory Compat testing:
- 2/99 SMOC Compat-1, SMOC Release 2.0, FSW Release 2.0
- 5/99 SMOC Compat 1.5, SMOC Release 2.2, FSW Release 2.1
- 7/99 SMOC Compat 2.0, SMOC Release 2.3, FSW Release 2.3
- 8/99 SMOC Compat 2.5, SMOC Release 2.3,FSW Release 3.0
- 10/99 SMOC Compat 3.0, SMOC Release 3.0, FSW Release 3.0
- 1/00 SMOC Compat 4.0, SMOC Release 3.1, FSW Release 3.1
Mission Simulations
- 6/99 Mission Sim-1, Use Release 2.2, IOC simulation
- 7/99 Mission Sim-2, Use Release 2.3, Sim#1 + execution of Sci Plan, plus L0 and L0.5 SDP
- 12/99 Mission Sim-3, Sim#2 + Green Card Testing (Power Cycle, Loss of Comm, SCU reboot, Cold Battery, PDU Reboot, SIís not going to HV, TAS Failure, RPI FSW load, Watchdog Timer Reset, V/T-Curve change, MMM Overwrite), also included Lights Out Ops and Science Data Processing.
- 1/99 Mission Sim-4, Final IOC Launch Script exercised, with two days of nominal operations simulations.
- 2/23 Mission Sim-5 Table-Top Sim + Green Cards to maintain FOT proficiency.