Editor: J. L. Burch
SwRI, P.O. Drawer 28510
San Antonio, TX 78228-0510
tel: (210) 522-2526
e-mail: jburch@swri.edu
The HENA team has decided on a final instrument design, which includes the collimator, door, foils, and start and stop MCPs from INCA and the solid state detector, imaging amplifiers, and digital and analog electronics from the originally proposed HENA. This new design preserves the excellent mass analysis capability of HENA while achieving the higher angular resolution of INCA.
Discussions on the MENA design have been ongoing
since the first team meeting. The alternatives are to increase
the geometric factor and UV rejection of the proposed MENA, which
has good mass separation or to go the slit-camera, TOF- only approach
proposed by Dave McComas at the first team meeting. As agreed
to at that meeting, Mei-Ching Fok has run simulations for hydrogen
and for all ions at several different energies. The results of
these simulations can be found at ftp://cyclops.msfc.nasa.gov/pub/IMAGE.
It appears that for this particular model mass analysis is only
needed for energies below about 5 keV. A decision will be made
on July 31st on which design to pursue for image.
MRR Meeting Draft Agenda
10-12 September 1996
Sept. 10: IMAGE Instrument and Science Review
8:30-8:45 | Welcome and Introductory Remarks | ||
8:45-9:00 | Meeting Objectives and Meeting Logistics (Burch) | ||
9:00-9:30 | IMAGE Mission Planning (Fuselier) | ||
9:30-10:15 | RPI Instrument Requirements Review (Reinisch) | ||
10:00-11:00 | FUV SI Requirements Review (Mende) | ||
11:00-11:45 | FUV WIC Requirements Review (Spann) | ||
11:45-13:00 | Lunch | ||
13:00-13:45 | EUV Requirements Review | ||
13:45-14:30 | HENA Requirements Review | ||
14:30-15:15 | MENA Requirements Review (Pollock) | ||
15:15-15:30 | Break | ||
15:30-16:15 | LENA Requirements Review (Smith) | ||
16:15-16:45 | CIDP Requirements Review (Gibson) | ||
16:45-17:30 | Integrated Systems Review (Gibson) | ||
17:30-18:00 | Action Items and Planning for Next Day (Burch) | ||
Sept. 11: IMAGE Spacecraft Review | |||
Meeting Logistics Announcements (Gibson) | |||
Project Organization, Roles and Responsibilities, Program Schedule (Gibson) | |||
Mission Overview (Burch) | |||
Break | |||
Level I Requirements, Mission Requirements, Mission Systems Engineering, Flight Assurance, Flight Safety (SwRI) | |||
Lunch | |||
Summary Review of Instrument Requirements (Gibson) | |||
Spacecraft Requirements (S/C Contractor) | |||
Action Items Review (Gibson) | |||
Sept. 12: IMAGE Spacecraft Review (cont'd) | |||
Meeting Logistics and Announcements (Gibson) | |||
Tour of S/C Contractor's Facility | |||
Launch Vehicle Briefing (GSFC) | |||
Break | |||
Ground Segment Requirements (GSFC) | |||
Lunch | |||
WTR Facilities Briefing (WTR Team) | |||
Action Items Review and Assignments (Gibson) | |||
Splinter Group Meetings and/or Splinter Group Reports |
It is essential that at least one person be present
to represent each instrument. The entire team is invited, and
we hope that as many members as possible can attend.